M.A.D. PRO
Aluminized bituminous sheet for acoustic insulation.
Product variations:

MAD PRO is a bituminous acoustic sheet reinforced with mineral loads and an aluminized coating. Its mass provides excellent acoustic insulation, acting as an anti-resonant element on one side, as a plastic element between rigid elements, or as a membrane resonator between spring elements. Additionally, it is characterized by its excellent fire performance (bs1d0), functioning as a vapor barrier and as a thermal reflector in cavities.
Advantages & Benefits
- By adhering to galvanised steel sheets, it improves the resonance of the sheet.
- By increasing the insulation at low frequencies, cavaties used can be kept to a minimal size.
- By increasing the mass of lightweight walls, a higher acoustic performance is achieved.
- It shifts the resonance frequencies of the rigid elements making the insulation stronger.
- Between insulators, it transforms acoustic energy into dynamics, improving insulation at low frequencies.
- Excellent performance in fire reaction testing (bs1d0).
- Acts as a vapor barrier.
- In the cavity, it shows thermo-reflective behavior.
- Allows its combination with perforated or porous surface elements to optimize acoustic insulation.
- The membrane provides the system with a fire reaction of Bs1d0 without the need for covering.
Instruction for Use
Preliminary OperationsIn systems between panels: Following the instructions and recommendations of the manufacturers of plasterboard, the framework will be fixed to the substrate, including sealing strips.
On the ceiling, first, the mechanical resistance of the damper system and the framework must be checked.
Next, the first plasterboard sheet is fixed to the supporting structure using self-tapping screws.
Ensure that this sheet is dry, clean, and free from foreign bodies. In direct systems: Following the instructions of the plasterboard manufacturers, it is recommended to install sealing strips around the perimeter of the framework.
Install directly with staples, contact adhesive, or using self-adhesive (in the AA version).
Lift the compound (board + membrane) and fix directly to the supporting structure using plasterboard fixing systems.
Avoid joints greater than 1 mm between sheets. Installation of Danosa Acoustic Membrane M.A.D. PRO:Due to its good fire reaction performance, the membrane can be installed directly after perforated and/or decorative solutions.For typical plaster partition solutions, the following points are recommended:On walls
Start by cutting full pieces of M.A.D. PRO to the same height as the partition. Offcuts will be used for smaller sections or finishing.
It can be applied with mechanical fixing systems or with bonding systems.
A. Mechanical Fixing
Once the piece is placed squarely with the surfaces, one person will hold it at the top, while another begins stapling the top. Then, one person releases and the other continues applying staples.
To maintain the continuity of the membrane, the M.A.D. PRO has a rebate on the edges that must be aligned.
The second plasterboard sheet is screwed to the supporting structure using self-tapping screws.
It is important to stagger the joints with the first sheet to avoid leaks. B. Adhesive
A layer of contact adhesive Glue-Dan Acustic 1 is applied to the first plasterboard sheet using a short-pile roller. The recommended coverage for perfect adhesion is 125 g/m².
In the same way, and on a clean surface where the membrane has been placed, apply another layer of adhesive with the same coverage to the M.A.D. PRO.
Prepare the pieces and, after 15 minutes, begin installing the membrane.
Place the piece squarely with the surfaces and start adhering it from the top and from the joint with another membrane.
Press down to ensure there are no air pockets.
To maintain the continuity of the membrane, the M.A.D. PRO has a rebate on the edges that must be aligned.
Screw the second plasterboard sheet to the supporting structure using self-tapping screws.
It is important to stagger the joints with the first sheet to avoid leaks.
The total adhesive coverage per square meter is 250 g.On the ceiling
Start by cutting M.A.D. PRO pieces transversely to the roll at a distance of 1.2 m. This results in pieces of 1 x 1.2 m². Offcuts will be used for smaller sections or finishing.
It can be applied with mechanical fixing systems or with bonding systems following the same steps as described for walls.
It is possible to work directly on the ceiling by fixing the membrane to the first plasterboard sheet or, alternatively, work on the floor by applying the membrane to the second sheet.
In this latter case, after fixing the membrane with staples or adhesive, the membrane and second sheet are lifted using a mechanical lift.
This assembly is screwed to the primary-secondary ceiling structure using self-tapping screws.
It is important to stagger the joints with the first sheet to avoid leaks. Note: DPS: Acoustic Insulation Work Manual. Details of Specific Points.
On the ceiling, first, the mechanical resistance of the damper system and the framework must be checked.
Next, the first plasterboard sheet is fixed to the supporting structure using self-tapping screws.
Ensure that this sheet is dry, clean, and free from foreign bodies.
Install directly with staples, contact adhesive, or using self-adhesive (in the AA version).
Lift the compound (board + membrane) and fix directly to the supporting structure using plasterboard fixing systems.
Avoid joints greater than 1 mm between sheets.
Start by cutting full pieces of M.A.D. PRO to the same height as the partition. Offcuts will be used for smaller sections or finishing.
It can be applied with mechanical fixing systems or with bonding systems.
A. Mechanical Fixing
Once the piece is placed squarely with the surfaces, one person will hold it at the top, while another begins stapling the top. Then, one person releases and the other continues applying staples.
To maintain the continuity of the membrane, the M.A.D. PRO has a rebate on the edges that must be aligned.
The second plasterboard sheet is screwed to the supporting structure using self-tapping screws.
It is important to stagger the joints with the first sheet to avoid leaks.
A layer of contact adhesive Glue-Dan Acustic 1 is applied to the first plasterboard sheet using a short-pile roller. The recommended coverage for perfect adhesion is 125 g/m².
In the same way, and on a clean surface where the membrane has been placed, apply another layer of adhesive with the same coverage to the M.A.D. PRO.
Prepare the pieces and, after 15 minutes, begin installing the membrane.
Place the piece squarely with the surfaces and start adhering it from the top and from the joint with another membrane.
Press down to ensure there are no air pockets.
To maintain the continuity of the membrane, the M.A.D. PRO has a rebate on the edges that must be aligned.
Screw the second plasterboard sheet to the supporting structure using self-tapping screws.
It is important to stagger the joints with the first sheet to avoid leaks.
The total adhesive coverage per square meter is 250 g.
Start by cutting M.A.D. PRO pieces transversely to the roll at a distance of 1.2 m. This results in pieces of 1 x 1.2 m². Offcuts will be used for smaller sections or finishing.
It can be applied with mechanical fixing systems or with bonding systems following the same steps as described for walls.
It is possible to work directly on the ceiling by fixing the membrane to the first plasterboard sheet or, alternatively, work on the floor by applying the membrane to the second sheet.
In this latter case, after fixing the membrane with staples or adhesive, the membrane and second sheet are lifted using a mechanical lift.
This assembly is screwed to the primary-secondary ceiling structure using self-tapping screws.
It is important to stagger the joints with the first sheet to avoid leaks.
Indications and Important Recommendations
- For very heavy ceilings, it is recommended to use a ceiling grid system consisting of primary and secondary profiles. This system helps to spread loads if any shock absorber anchorage point breaks. See SPD 4.3.
- The ceiling dampers are always anchored to the floor joist or a reinforcing construction element. See SPD 4.2
- The facade cladding in a building must end at the dividing wall between different users. See SPD 2.1
- In dry wall cladding for heights over 4 m, we recommend the use of elastic fasteners. See SPD 2.5
- Gypsum plasterboards must always be anchored to the galvanised steel auxiliary structure, never use plate-plate screws.
- Partition walls must be plastered with at least 1 cm. See SPD 3.
- Partition walls should not be anchored to structural elements (except for roofs in dwellings) such as pillars and facades. In order to maintain the stability of the system, the tiling element must be bonded to the internal floating partition walls.
- It is not possible to perforate with installations in the proposed solution in commercial premises located in tertiary buildings or commercial ground floors in residential buildings. See SPD 2.3 and SPD 4.4.
- In solutions with perforated finishes or in cavities, the aluminized side helps to promote the reflection of heat towards the interior of the room.
Presentation
- Length (cm): 900
- Width (cm): 100
- Thickness (mm): 3
- Surface (m²): 9
- Product code: 610041

Technical Data
Concept | Value | Standard |
---|---|---|
Mass per unit area (nominal) (kg/m²) | 5 | EN 1849-1 |
Improvement to airborne noise on laminated gypsum board partition, ΔR (dBA) | 4* | EN 140-16 |
Insulation improvement at 125 Hz (between rigid elements) (dB) | >5* | - |
Reaction to fire | Bs1d0 | EN 13501-1 |
Longitudinal tensile strength (N / 5cm) | 513 | EN-12311-1 |
Transverse tensile strength (N / 5cm) | 462 | EN-12311-1 |
Resistance to tearing (nail shank) (N) | 200±3 | EN 12310-1 |
Thickness tolerance (%) | 10% | EN 823 |
Mass tolerance (%) | 10 | EN 1849-1 |
Tolerance Length and Width (%) | 5% | EN 822 |
Addtitional Technical Data
Standards and Certification
- The sound certifications are the result of tests in an approved laboratory.
- *For any questions about information on the tests, please consult our Technical Department.
Environmental Information
Concept | Value | Standard |
---|---|---|
Volatile organic compounds (COV's) (µg/m³) | 50 | ISO 16000-6:2006 |
Content of recycled raw material (%) | 15% | - |
Post-consumer recycled content (%) | 60% | - |
Manufactured in | Fontanar (Guadalajara) España | - |